Project Overview

The campus included a new build Primary School and new build Post Primary School for Department of Education and Skills. Luttrellstown single site campus consisting of 650 Person Post Primary School for Luttrellstown Community College, a 16 classroom school for Scoil Choilm, shared general purpose hall for Scoil Choilm Junior and Senior School and extensions to the existing Scoil Choilm School

Construction process

Western were tasked with the design and build of a 650 pupil post primary school, 16 classroom school, shared GP Hall and extensions to existing school for Department of Education and Skills. As Lead Design and Build Contractor, Western Building Systems were responsible for all design elements, site development works, mechanical & electrical installations. The building was a permanent rapid build school consisting of structural steel frame, precast concrete floors and block fair faced walls. The building was a complete turnkey solution which was completed within a 52 week programme.

Handover

Western carried out this project concurrently with six other schools as part of the Build Schools Framework. All works were carried out as Lead Design and Build Contractor. This includes off-site and on-site works.

The high standard of construction has also been demonstrated by Air tightness test results, thermographic test results and BER ratings achieved for each building  as follows:

Air-tightness test Results

Scoil Choilm 16 class school – 2.83 (m3/hr)/m2 at 50 PA
Scoil Choilm GP Hall- 2.74 (m3/hr)/m2 at 50 PA
Luttrellstown Community College – 2.97 (m3/hr)/m2 at 50PA
BER Rating of Buildings– A3